  • 2004 | Frontage areas main cemetery

    Planning: 2004
    Construction time: 2004
    Area: Approx. 1.600 m2
    Building costs: Approx. 144.000,00 €
    Client: Erfurter Verkehrsbetriebe AG (Erfurt public transport) with City of Erfurt, public gardens and cemeteries department

     

    Responsibility of the planning office Blattwerk

    » Open space planning

    » Performance phases of 5 and 8 HOAI (the German Free Ordinance for Architects and Engineers) for the mentioned area of responsibility

  • 1999 | Route extension Binderslebener Landstrasse

    Planning: 1999 - 2004
    Construction time: 2000 - 2005 in 6 stages of construction
    Length: Approx. 3.6 km
    Building costs: Approx. 1.7 m €
    Client: Erfurter Verkehrsbetriebe AG (Erfurt public transport)

     

    Responsibility of the planning office Blattwerk

    » Landscape management support planning, complete commissioning of the open space planning for track section Hauptfriedhof (main cemetery), construction supervision for other track sections, artistic construction supervision for the entire development, ecological construction supervision

    » Phases 1 to 8 HOAI (the German Free Ordinance for Architects and Engineers) for track section Hauptfriedhof (main cemetery),  phase 8 for other track sections

  • 1999 | Engelsburg, Erfurt

    Planning: 1999 — 2000 
    Construction time: 2000
    Area: Approx. 450 sqm
    Building costs: Approx. 110,000.00 €
    Client: City of Erfurt; Municipal building department

     

    Responsibility of the planning office blattwerk

    » Complete commissioning of the open space planning

    » Phases 1 to 8 HOAI (the German Free Ordinance for Architects and Engineers) for the mentioned field of responsibility

  • 1998 | Leipziger Platz, Erfurt

    Planning: 1998 - 1999
    Construction time: 2000
    Area: 0.55 hectares
    Building costs: Approx. 350.000,00 €
    Client: City of Erfurt, public garden and cemeteries department

    Responsibility of the planning office Blattwerk

    » Complete commissioning of the open space planning, fountain with an underground fountain room, routing planning for fresh water and sewage, concept of the shift of a transformer away from Leipziger Platz

    » Phases 1 to 8 HOAI (the German Free Ordinance for Architects and Engineers) for the mentioned field of responsibility

    » special planning tasks of the sector plannings in an interdisciplinary cooperative partnership with sub-planners

  • 1996 | Extension of the Erfurt tramway, Leipziger Strasse

    Planning: 1996 - 2000
    Construction time: 1998- 2000 in 10 stages of construction
    Length: Approx. 2,7 km
    Building costs: Approx. 1.6 m € in
    Client: Erfurter Verkehrsbetriebe AG (Erfurt public transport) with City of Erfurt, public gardens and cemeteries department

     

    Responsibility of the planning office Blattwerk

    » Landscape management support planning, open space planning, planting of trees, protective bioengineering measures at Galgenberghang, construction supervision for other track sections, compensation spaces, artistic construction supervision for the entire development

    » Phases 1-5 landscape management support planning, Phases 1 to 8 HOAI (the German Free Ordinance for Architects and Engineers) for the mentioned field of responsibility in site planning

  • 1996 | Open space design Unteres Schloss (Lower Castle), Greiz

    Planning: 1996 - 1998
    Construction time: 1997 - 1999 in two stages of construction
    Area: Approx. 1.2 hectares
    Building costs: Approx. 0.85 m. €
    Client: City of Greiz; Civil Engineering office

     

    Responsibility of the planning office Blattwerk

    » Complete commissioning the Open space design including preservational integration of  historical bridge from the 17th century, lighting

    » Phases 5 to 8 HOAI (the German Free Ordinance for Architects and Engineers) for the mentioned field of responsibility